Most of September will be used for documentation.
The first 3 weeks of October will be used making the connector and its
controller program the Config Manager.
September
Su Mo Tu We Th Fr Sa
1 2 3 4 5 6 7
; Schedule
8 9 10 11 12 13 14 ; Requirements Analysis
& Design
15 16 17 18 19 20 21 ; Design Doc
22 23 24 25 26 27 28 ; API Spec ; includes Connector protocals
29 30 ; Socket Connector
& Config Manager
October
Su Mo Tu We Th Fr Sa
1 2 3 4 5
; Socket Connector & Config Manager
6 7 8 9 10 11 12 ; Socket Connector
& Config Manager
13 14 15 16 17 18 19 ; Socket Connector & Config Manager
20 21 22 23 24 25 26 ; Demuxer & Muxer
27 28 29 30 31 ; Auss
Lib
November
Su Mo Tu We Th Fr Sa
1 2 ; Auss Lib
3 4 5 6 7 8 9
; Auss Lib
10 11 12 13 14 15 16 ; Pipe Splitter
17 18 19 20 21 22 23 ; User manual
24 25 26 27 28 29 30 ; Reference
December
Su Mo Tu We Th Fr Sa
1 2 3 4 5 6 7
; Developer Reference
8 9 10 11 12 13 14 ; Example Programs
15 16 17 18 19 20 21 ; Example Programs & Demo